Installations
Underground Storage Tank and/or Piping Installations
Installation of underground storage tanks (USTs) and/or piping requires an application (UST-6) to be submitted and approved by the UST Section prior to the UST system's installation. Below are links to documents with information on installation requirements.
We are excited to announce that the Public Portal for UST-6 Tank & Piping Installation Applications is now live as of December 15, 2025!
In preparation for the launch, the AccessDEQ development and production teams created a public help website that includes helpful information, user guides, and tutorial videos. You can access it here: Portal Help.
For more information about the Permitting Transformation Program and to access the AccessDEQ portal, visit: AccessDEQ.
Users can also go directly to the AccessDEQ Portal using this link: AccessDEQ Login. Users will be directed to the login screen, where users can register for a new account or log in.
For detailed instructions on accessing and using the portal, including how to submit an application, please refer to the ‘Underground Storage Tank’ User Guide, available here: Portal User Guides. Please note that this guide will be updated regularly, so we encourage you to check back often for the latest version.
Now that the portal is live, new installation applications will no longer be accepted via email. All applications will need to be submitted through the portal. However, if a project’s UST-6A (Pre-Installation) application was previously submitted to our inbox using the older PDF/Word form format, please submit the project’s corresponding UST-6B (Post-Installation) application in the same PDF/Word form format to our email inbox. Here is the link to PDF/Word version of UST-6 application: Application to Install or Replace Underground Storage Tank Systems (UST-6).
- Secondary Containment Performance Standards for UST Systems after 11/1/2007
- New permitting process for new UST System Installations
- UST System Installation Inspection Overview
- UST System Installation Approval Modifications
- Approvals for Tanks Monitored Using Dry Interstice Monitoring Methods
- Tank Interstice Testing Protocols (3rd party certified tightness tests)
- Dry Tank Position Sensitive Sensor Installation Instructions
During installation, you are required to have two inspections conducted by the UST Section. The first inspection is of the tank prior to placement in the ground. The second is after installation of the piping but prior to back-filling. You are required to schedule these inspections a minimum of two work days (not including weekends or holidays) prior to the day you propose to commence the activity. Prior to finalizing the schedule of the installation activity, such as scheduling tank delivery and a crane, it is recommended that you contact the inspector so that a mutually convenient inspection date may be arranged on or around your proposed date. Additionally, if you need to obtain a “One-Time Fuel Delivery” for testing purposes after installation, please advise the inspector prior to the inspection date. This authorization can be coordinated during the inspection process (note that overfill and spill prevention equipment will need to be installed). You should provide at least one week notice to ensure your proposed installation date is available and on the inspectors calendar.
Note that inspections cannot be scheduled for weekends or state holidays.
If you wish to use petroleum or another regulated substance as ballast during installation, then you need to follow the procedures outlined in Guidelines for Approval of One-Time Fuel Delivery at Install for Ballasting to receive approval for a one-time placement of a regulated substance in the UST system.
If you did not use a regulated substance for ballast, then you will need to get approval to use petroleum or another regulated substance for line and leak detector testing during the final stages of installation. To receive this approval, you need to follow the procedures outlined in Guidelines for Approval of One-Time Fuel Delivery at Install for Testing.
After the UST system installation is completed, refer to Secondary Containment O & M Requirements for UST System and Components Installed or Replaced after 11/1/2007 for information on the leak detection and periodic testing requirements of each part of the UST system.
Permits and Inspection - Installation Forms
If you have any questions about the installation application process you can contact Matt Wegner at (919) 707-8163 or Mickey Roberts at (919) 707-8162 or Matt Mahler at (919) 707-8172.
| UST System Design and Installation Seminar for Engineers and Contractors Slideshows (2012) | |
|---|---|
| Introduction | |
| UST System Design I | |
| UST System Design II | |
| UST System Design III | |
| PreInstall (UST-6A) | |
| Installation Inspection - Contractors | |
| PostInstall (UST-6B) |